Aggregator
The following cavity histories have been updated: 1L12-6
The following cavity histories have been updated:
1L12-6
Username: holben
Date/Time: 03-09-26_14:58:17
RF Status: Bad
Tuner Status: Good
Comment: Replaced Klystron L3 #206 with Stellant #228. Waiting to be tested.
Special Instructions: , HPA breaker tripped
Maintenance Tag: Component: Tube {Removed SN: L3 #206, Replacement SN: Stellant #228}
IIX1L02_gDsRt increased at 1420
GMES sum didn't change from period before it was turned off. Higher gamma rate coincided with restoration of gradient. I believe the electrometer was supposed to be swapped today but I deleted the ATLis email so I can't be sure. Dose rate is back down now.
Box Supplies Turned on and Cycled Once
The following box supplies were TURNED ON AND CYCLED ONCE by version 2-16 of the Box Supply Cycling Script:
ARC1A Ramp Rate = 7.400 A/s
ARC3A Ramp Rate = 9.294 A/s
ARC5A Ramp Rate = 9.307 A/s
ARC9A Ramp Rate = 8.832 A/s
RSEP9A Ramp Rate = 4.865 A/s
COMMENT ON Gun2 photocathode Heat and Activation - March 2026
COMMENT ON RF work for 2026 HCO
East Arc Box supplies are good to turn on
Received word from Operability that the LCW manifold was put back in place. The East Arc Box supplies are good for turn on. Arc 1, 3, 5, 9, and RSEP9.
Arc 7 still a no go due to YBBS06.
DC power has pulled out E-Stop on the affected box supplies so we can turn them on remotely.
Box Supplies Turned on and Cycled Once
The following box supplies were TURNED ON AND CYCLED ONCE by version 2-16 of the Box Supply Cycling Script:
ARC2A Ramp Rate = 7.131 A/s
ARC4A Ramp Rate = 10.144 A/s
ARC6A Ramp Rate = 8.835 A/s
ARC8A Ramp Rate = 11.455 A/s
ARCAA Ramp Rate = 11.756 A/s
RSEP8A Ramp Rate = 10.544 A/s
XSEP2T Ramp Rate = 5.386 A/s
XSEP4T Ramp Rate = 5.186 A/s
XSEP6T Ramp Rate = 9.209 A/s
XSEP8T Ramp Rate = 16.057 A/s
XSEPAT Ramp Rate = 15.209 A/s
PSS Procedure Screen Controls Updated
COMMENT ON Relocate B38 & B67 RTU thermostats
Latest update is next full-on maintenance day will not be until next week (week of 3/16). I take it you are looking for a time when the BoxPSs will be off. There will be an opportunity with this condition present tomorrow, Tuesday 3/10, between 0730 and ~noon. Would you be ready to do this work tomorrow, or want to wait until next week?
Updated MXM3S03 shunt current limiting coefficient
COMMENT ON Setup injector with 140kV gun for Spring 2026 Run
Set Hall A to Inactive in MSS
Do not turn on East arc Box supplies
Received a report from Operability that an LCW manifold was removed during YBBS06 work, affecting the East Arc Box supply magnet strings. This includes Arc 1, 3, 5, 7, 9, and RSEP9.
DC power has enabled the E-Stop on the affected box supplies so they are not inadvertently turn on by Ops.
COMMENT ON PSS Video System Upgrade
ced2Epics modified EPICS PVs
COMMENT ON YBBS06 Swap
COMMENT ON Setup injector with 140kV gun for Spring 2026 Run
COMMENT ON Relocate B38 & B67 RTU thermostats
1D dipole (MBO0I06) setpoint for 140 kV operations
Looked back at the 2024 run when we were running a 140 kV Gun to see what the MBO0I06 dipole was set at for 1D running.
Looks to be 298 mA.
The dipole setting now for 200 kV is 372 mA.
The button / control screen Ops uses to set this magnet will need to be updated for that value. Perhaps we should also add in another row on the table for this energy and dipole current.










