Aggregator

COMMENT ON 1L07 JT stem assembly replacement

4 days 6 hours ago
Log Number: 4551389Logbook(s): Body: 

Removed and swapped JT stem assembly with a new one. I didn't see any issue with the pulled stem assembly or the seat inside the end can.
Reinstalled JT actuator & set the seating force & LVDT position indicator and verified valve closure. Circuit held 8psi / no bleed down over a 24-hour period.

fhumphry

Hall D - Daily report

4 days 7 hours ago
Log Number: 4551383Logbook(s): Body: 

Instrument Air compressor PM and replacement of pressure reliefs
GEM ~ gas recovery system procurements
Other scheduled maintenances
TAGM fiber bundle production

spiegel

C100-02R Acceptance Testing Swing Shift

4 days 16 hours ago
Log Number: 4551380Logbook(s): Body: 

Completed Tuner characterization for cavity 6.
Then did the gradient ramp for cavity 6. Emax at 20.8 MV/m MV/m - CARM (gamma) limited
FE Onset at ~12.5 MV/m
Max dose rate ~ 6 R/hr at 20.8 MV/m
Attempted one hour at 20.8 MV/m.
Completed FE vs E measurement

drury

COMMENT ON Install 8 kW circulators in 1L09

4 days 19 hours ago
Log Number: 4551378Logbook(s): Body: 

Spent time tidying up cables and connections in HPA. Possibly need of replacing couple of RF cables and using elbows to help cables that need quite some bending. Klystron connection board in cavity #5 needs cable retermination. Work will continue Friday

xgomez

MOLLER install 10/29/2026

4 days 20 hours ago
Log Number: 4551375Logbook(s): Tags: Entry Makers: jonesBody: 

•Moved two MPS shielding blocks.
•Transport the MPS IC electronic rack to hall
•Worked on the upstream beamline girder and adjusted with shims.
•Target group doing leak detection on h2 piping expect to be done next week.
• Mapping of the TM0.

jones

Cryogenics Update

4 days 21 hours ago
Log Number: 4551374Logbook(s): Entry Makers: creelBody: 

Installed liquid nitrogen dewar #2 relief valves
Started cleanup of CHL2 SCN 2K cold box process piping
Crane scheduled for next Thursday to install CHL2 SCN cold box lid.
Installed additional relief valves on CHL2 vertical cold box
Continued removing racks from CHL control room, assembled second workstation table, and ran conduits.

creel

Hall C daily summary

4 days 21 hours ago
Log Number: 4551370Logbook(s): Body: 

Today Hall C technicians worked on.

Removing downstream beam line from target to gate-valve. with rad-con support.
Assembling filament extrusion project.
Meeting about NUCAT modifications.
Assembling welding paperwork package for weld examination.
Cross division work for Friday will be Fork lift practical with Facility's.

jnines

COMMENT ON SAM26 PSS replace the ILD air cylinder actuator

4 days 22 hours ago
Log Number: 4551369Logbook(s): Body: 

This task is now approved in the ePAS system. Need to schedule the best time to perform this task. While not in the direct area of ongoing work in the NL it is in the path to access those areas. we would need approximately one full day to perform this task if all goes as planned. Would like to perform this task next week if scheduling permits.

sbruhwel

Shift Information

Shift Day
CEBAF Program
MCC Crew Chief Deir
MCC Operators
Program Deputy Delk
Announcements

Access Status

Recent PSS History

recent pss history graph