Aggregator
COMMENT ON SAM25 PSS Miscallenous Repairs
COMMENT ON Plasma processing during the Fall 2025 SAM
Looks like they need a network connection in this area.
After talking with Brent the closet CST switch to that zone is NL17. There would need to be a cable installed upstairs from Z17 to the patch panel Z11.
If a cable needs to be installed then we will have to do an ATLIS with epas for the work.
This is a bit of a short notice to get this done with the planning requirements/policies in place and work load. but we will try our best to accommodate.
So the 2 options are:
1. Try to extend the cable downstairs from NL05 - can be done today
2.
COMMENT ON CUP ELEC-SWBD-TL100 Meter Installation
From task owner, rough-in portion of this task is complete. Waiting on chiller commissioning (see related ATLis) to complete before scheduling outage for meter tie-in. This outage will not affect the chillers, so it will not affect service building HVAC. With that understanding, this can proceed whenever works best for FML.
Please comment ahead of time on when the outage is planned and I'll add it to the SAM Cal. (Note: We 12/17 schedule date is nothing more than a placeholder)
iocsoftinjvac2 restored
iocsoftinjvac3 restored
HOLD B21 21-E1-L Meter Installation
COMMENT ON B45, B40 Meter Installation
SCHEDULED B45, B40 Meter Installation
iocsoftinjvac3 restored
iocsoftinjvac3 restored
Currently Disabled Alarms_all
The Following Alarms Have Been Disabled For Over a Week
===============================================================
09/03/2025 15:17:13
INJECTOR
samari
SAM 2025!
---------------------------
09/03/2025 11:25:25
HALLD
samari
SAM 2025!
---------------------------
09/03/2025 11:25:15
HALLC
samari
SAM 2025!
---------------------------
09/03/2025 11:25:04
HALLB
samari
SAM 2025!
---------------------------
09/03/2025 11:24:51
ACC
samari
SAM 2025!
---------------------------
APPROVED PACS-Hardware Upgrades (Canon Hut, LERF, ACS, MCC)
Spoke with task author and confirmed that at each of the four locations they do not expect to need to take down a whole electrical panel. Single breaker / switch for the PACS panel at each location. If that changes, will pause and coordinate the necessary panel outage.
Spoke with LERF Work Coordinator, ACE team, and Ops team regarding this work. No issues from any stakeholder raised, ordering can be whatever works best for FML/subcontractor.
Task author will comment where the subcontractor will be working at a given time.
Task approved and added to SAM Cal.
Follow-up Re: Lowering 2L25 to Investigate Leak
Helicity Signals at 30 Hz Default
iocse1 restored
iocsoftinjvac2 restored
Lowering 2L25 to Investigate Leak
At around 8:30 pm last night, a rise in the 2L25 insulating vacuum was observed. Over the course of the next few hours, the vacuum reading rose from the -5 range to the -3 range. The liquid level before this rise had been relatively stable around 90%.
After the vacuum reading rose to the -3 level, there were several instances overnight of a heat bubble going through the module, the liquid level dropping to around 85%, and the vacuum improving.










