Aggregator
COMMENT ON Tunnel GW Catch Pans
PTW-95863 does not exist. Looked back at previous ATLiss for drip pan work, found PTW-9583 -- Leak Repair Accelerator Tunnel, on-issue up until 1/29/27. This seems like the right one. If not, please comment with the right one.
Linked previous ATLiss of related work.
APPROVED CHL II Cooling Tower Brace Foundations
Discussed with F&O -- for those interested, yes, this is similar to the vibrations that were seen on the NAB Cooling Tower (B67) for the West Arc LCW system that eventually led to a pinhole leak in the cyclone separator.
To confirm, CHL Cooling Tower functionality will not be impacted when constructing these concrete pads, correct?
Please attach supporting documentation such as Dig/Excavation Permit and subcontractor AHA to this ATLis when you have it.
COMPLETED Hall A Dump Camera Box Shielding
COMMENT ON (SAM26-27) Hall D line BCM Temp controller conversion
first target for the rollout of this new controller is going to be IPMAD00. its a non-BLA cavity and is the easiest to access the downstairs portion if we have any need to. initially we will only convert this controller to prove the new controller in the field and let it get some run time before moving to convert the other two. currently we are waiting on ACE to assign a network port and install a network cable.
Program Deputy Summary, presented 2026-11-05
COMMENT ON MO Outage in Preparation for Bldg 85 Panel PMs
Morning all, this is the reminder that tomorrow at 10 am, the entire MO (and LO) distribution system will be turned off.
If you have any sensitive equipment that needs to be powered down before this happens, please do so between now and tomorrow at 10 am.
Thank you.
COMMENT ON Plasma processing during the Fall 2026 SAM
COMMENT ON 2026 SAM LCW Controls Calibrations
APPROVED Dominion Energy 40 and 33 MVA Substation PM
1L07 Update
COMMENT ON Upgrade 1L08 to a C75 zone.
COMMENT ON 26/27 SAM Power Supply Flushing
Hall D - Daily Report
COMMENT ON 2026 SAM LCW Controls Calibrations
Survey and Alignment work summary
ATLis Comments Daily Digest
COMMENT ON Wien filters high voltage evaluation
COMMENT ON Wien filters high voltage evaluation
ACG Report
RF 1L08 Upgrade network infrastructure installation complete
-UPS NMC nl08b12ups01 has been configured.
Verified communication to all RF 3.0 Chassis's in NL08 from the new softIOC "iocsoftnl08rf"
Started design of the new vac-summary screen generator.










