Aggregator
ACG Report
New NDX ioc setup for 1L08. Troubleshooting comm issues to the device.
Completed development for the new vac summary screens
ATLis Comments Daily Digest
COMMENT ON Injector Laser Hut Fiber Installation (Helicity Signals)
Fiber trunks and signal cable installed from ISB to Laser hut. Installed fiber chassis in laser hut and dressed in the fiber trunks.
Tomorrow we will install the network switch in the laser hut and focus on getting the fiber dressed in to the fiber chassis upstairs.
Cumbia
Latosky
Sawyer
COMMENT ON Bldg. 85-HVAC Repairs - perimeter offices
MOLLEr install 11/11/2026
• Weld inspection on the Upstream Spectrometer Girder Support done.
• Setup the Work & Storage area for the Barite Wall materials. Start bring down materials.
• Completed welding on 2 of 4 stands for detector cable support.
• Powered up the control rack for the MOLLER magnets and PS.
Thanks for putting in the HaLISt for work at the Hall A truck ramp.
Tentatively on 11/23 and 11/24, but he will confirm dates with vendor.
See the HaList for updates!
Grommet and Cable Pass-througs Installed
Cryogenics Work Update
• ESR1 C3: Replacement of the IQ-1000 with an SEL-451 is currently in progress. Techs found burnt varistor on circuit board.
• CHL2 K100: CV22457 T3 Control Positioner regulator was found leaking from the diaphragm. The regulator was replaced, and the system was returned to service. Completed.
• Continuing CHL2’s 2K Cold Box vacuum space & backfills with GN2 to dry the superinsulation
• 3 CHL2 LHe Dewar u-tubes installed
• Replaced a HDR LN2 dewar relief valve
• Continuing CHL2 relief valve replacements
Hall C daily summary
Today Hall C technicians worked on.
Machining MOLER Barite shield wall assembly parts.
Preparing Moler Barite concrete attachment plate for welding
Assembling Filament extrusion project.
Cleaned out Shelving from EHS and relocated to laser room.
Repairing shop engine lathe.
Had a meeting with DSO about BNL forklift incident
COMMENT ON Swap PSU for IOCNL2 Camac Crate 13
COMMENT ON SAM26 Continuation of PSS Video System Upgrade
Finished running cables to the cameras inside the laser hut. Setup and tested cameras network connections to the MCC display and they are functioning correctly. Still need to finish setup and testing for viewing on monitor at the laser hut and final adjustments. Will finish with setup and testing after other groups are done with there work inside the laser hut. Liliia, Mike, and Scott










