Aggregator
COMMENT ON CEBAF Gun High Voltage Conditioning with Kr Gas
Operator SIGN IN
Power Calculator doesn't like leading decimal points
The Power Calculator is used to determine the Power, Current, or Energy given the other two (and the Duty Factor). When using it for the Injector, one works in W & keV. I've found that when inputting a leading decimal point, it is ignored, which leads to an erroneous answer. (If one enters a leading 0 first, or adds a leading decimal point after entering a number, it works.)
COMMENT ON SAM 2026 Box Supply Work Preventative Maintenance/interlock checks
Follow-up Re: Cryogenics Update
Cryogenics Update
Cryo and SRF attempted to install CMTF C100 Utubes but ran into a small interference issue which SRF corrected and utubes moved to tomorrow morning.
Removed transferline LTubes at 1L06 and 1L07.
Performed CHL1 C5 annual maintenance.
Restored CHL2 main compressors C1-C6 cooling water flow to oil and gas coolers.
Hall C Daily Summary
Tuesday Hall C TEC staff is working on "NUCAT" lead shielding support structure, 3D printing" MINI CAT " Quarts fixture, Manufacturing concrete anchor pieces for Hyper nuclear, also, modeling and printing filament extruder.
We do not expect any cross division support for Wednesday.
MOLLER Install 10/13/2026
• Completed LCW assembly for MOLLER PS and magnets
• Disassembled one Main Detector cable tray. Remove all Main Detector cable trays out of hall for welding work.
• Prepped for Upstream Girder Welding.
• Pulled 10 more Main Detector 100m cable bundles.
• Cleaned up hall for DOE tour
iocsoftw3spce restored
COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
Hall B SAM daily update
Gun HV Turned Off > 1kV
Verified HVPS current level baseline shift with applied HV
In today's first ramp up cycle we noticed HVPS current baseline increased at 206 kV, and went back to normal level during ramp down at 100 kV. In the 2nd ramp up cycle we noticed the onset of baseline shift appeared earlier at 140 kV. This indicates some current leakage in air side. Next, we will inspect the gun HV ceramic and the cable joint, and also remove the resistor tank and inspect the joints. After reconnection of gun HV cable, we will continue evaluation.
COMMENT ON Install C-100 style Vacuum Controls and Cable Install NL08 (2026 SAM)
COMMENT ON SAM26 Routine Maintenance of ODH Systems (Managed by SSG).
1L06/1L07 L-Tubes Removed
L-Tubes were removed from 1L06 and 1L07 return transferline locations. Guard vacuum connection was disconnected from 1L06.
1L06 RT valve motor was found spinning. This is likely an issue with the belt (stripped, broken). This will be repaired before PR U-Tubes are installed.
No other issues were encountered.
Survey and Alignment work summary
COMMENT ON SRI 3C12 Work
Work completed for now. Rotated the polarizer back to a horizontal polarization orientation. Check the optics and found both the inseratable mirror and window coating strip off in a band. This is caused by high energy synchrotron radiation. This was anticipated and will not fundamentally change how the SRI operates.










