Aggregator
COMMENT ON Install network switch
I'm ready to install the new switch in the CHL and the fiber patch cables in NLSB Zone 13. After discussing with Brad Cumbia, the switch will now be installed in the CHL Control Room rack 9 (one of the racks that isn't being removed) which will involve less movement of existing cabling down the road. Again, this work won't yet involve disrupting any currently active systems.
iocsoftmag restored
COMMENT ON (SAM 26-27) NDX/IDX installs
iocsoftmag restored
COMMENT ON MO Outage in Preparation for Bldg 67 Breaker PMs (Affects Bldg 85)
Changing outage time from noon tomorrow to 3 pm today!
I repeat, I will turn off the entire MO at 3pm today.
The breaker PM work starts tomorrow morning, and I have no guarantee the items that control building 85 power won't be touched.
System will be restored after the NAB panel PMs are complete.
Program Deputy Summary, presented 2026-10-12
Hall C work
Today Hall C is currently working on HKS detector stands, NUCAT drawing modifications, Shield block anchors, and Filament extrusion design, Monday we discovered a faulty turbo pumping station and tagged it for racon survey. Also had to get a working pumping station from Building 72 to hall to pump on LN2 U tube.
Jerry
Hall B SAM
Hall D Daily update
Tunnel Condition Walkthrough, part 2 of 2
Part 2 of the tunnel conditions walkthrough.
- In the West Arc, the LCW return shows evidence of water intrusion [figure:1]
- At the bottom of Exit Stair 6, there is a lot of rust staining [figure:2] [figure:3] [figure:4]
- In the West Arc, there is some concrete missing from the floor [figure:5]
- In the walkway near AA05, water intrusion [figure:6]
- Under the AA04 dipole, the slab under the support stand has been chipped [figure:7]
Tunnel Condition Walkthrough
MOLLER install 10/9/2026
Main accomplishments for week:
• 46 detector 100m cables bundles ( 8 cables per bundle) were installed between detector and DAQ bunker.
• Upstream cryo can installed. Piping connections between cryo cans installed but need some modifications.
• Four Main Detector Vertical cable support and trays were assembled.
• The CS06 and CS07 blocks, that were modified previous week, were transported back to Hall A from the CMSA and installed on the pivot platform.
ATLis Comments Daily Digest
iocsoftw3spce restored
iocsoftw3spce restored
ACG Report
Assisted with CAMAC recovery on iocea5 and iocea6
Restarted cmlog server










