Aggregator
iocsoftljwien restoration failed
iocsoftljwien restoration failed
ATLis Comments Daily Digest
ACG Report
BLA VME Test Stand Setup and Checkout:
-Software installed. The IOC and test screen are up. Now working through the card addressing and backplane setup with I&C so the IOC sees each card where it expects it.
seed lasers on
iocsoftljwien restoration failed
Follow-up Re: Follow-up Re: ISB Laser Room Rack Work
COMMENT ON SAM26 Routine Maintenance of ODH Systems (Managed by SSG).
COMMENT ON Gun prep chamber rebuild
Bake at temperature. There is an odor from heating the high temperature tape and insulation that we use evident as far away as the North Access stairwell - this should dissipate now that we are no longer increasing temperature. Bake will continue through Friday morning, when it will begin ramping down for NEG activation, and it should be at room temperature by Saturday. https://logbooks.jlab.org/entry/4552811
COMMENT ON PSS General maintenance tasks for SAM 2026
Hall B: Replaced the old 4-conductor cable with new 8-conductor cable from the Hall B junction box to the maglock junction boxes to accommodate the replacement of the maglocks at Hall B Access Doors 1 and 2. Completed all wiring connections at both ends. Installed and wired new maglocks at both doors. Final adjustments and operational testing of the maglocks remain to be completed.
L.Krylach, M.Beizer
gun bake update
Gun bake reached temperature around 2:30-3 this afternoon. The setpoint is 185C, with many of the parts reaching 200C with the control flange at 185C.
The gun ion pump and suitcase ion pump are slightly elevated: 2-3 nA for the gun rather than 1 or less, and 0.1-0.2 nA for the suitcase rather than 0. This is expected with the adjacent areas being at elevated temperatures.
Cryogenics Work Update
• Installed second of 3 LN2 u-tubes for CHL2’s 2K Cold Box
• Old CHL1 C3 compressor body was removed before installing replacement
• Started trick purge of CHL2’s 4 Cold Box to recovery system
CHL1 C3 electrical PMs - Completed.
HDR Cold Box EV318 Valve Leak-By Troubleshooting - In progress.
CHL1 Compressor Labeling - In progress.
CHL 1 Control Room Monitor - In progress
MOLLER install 11/18/2026
• Finished anchors for MPS bunker walls
• Welded support for TM4 LCW cable
• Welding on Upstream Spectrometer Girder Support complete. Area cleaned up.
• Flipped and prepped Beam Right Barite wall to accept Collar 2.
• Ran MOLLER magnet TM4 at 50A.
COMMENT ON PSS General maintenance tasks for SAM 2026
Installed an extension to the existing maglock junction box and pulled new 8-conductor cable from the junction box to the maglock junction box to accommodate the BSY gate maglock replacement. Completed all wiring connections on both ends in accordance with the drawing. Replacement of the old maglock and its wiring remains to be completed.
COMMENT ON Install 8 kW circulators in 1L09
Klystron for cavity #8 was hi-potted and it showed signs that tube needs conditioning. Also wiring of Klystron in cavity #6 needs to be looked at, which is related to the high body current trips we have experienced. Will get with SME to determine if tube in cavity #8 needs further conditioning or replacing and get wiring of Klystron for cavity #6 looked at.










