Aggregator
COMMENT ON Wien magnet work-CEBAF/Injector
MSSG:
Here to spread some joy and happiness for the Injector.
We just completed installation of vertical WIEN in the up beam Injector location it went flawless. The refurbed magnet was re-insulated, rust removed, electrical tested great, added new core and installation hardware, installed TCs to top and side of outer core halves, hooked up magnet to terminal block.
Mamun was working to install inert gas ports.
We will start building up the horizontal WIEN tomorrow, with any luck we will begin installing Friday.
COMMENT ON Tunnel Arc Magnet Flushing
MSSG:
The team did a real nice job in EA today carrying on with SAM dipole array flushing work. We enjoyed some time sharing what we do and how we do it with Jonathon Huff and appreciate his visit and eye opening as well.
This flushing work will continue on tomorrow in EA. Job well done team!
COMMENT ON 2026 SAM LCW Controls Calibrations
Correction: New East ARC pH sensor was configured but would not take the calibration procedure. The technician believes the issue is related to the pH cable used that was removed from a Emerson portable pH calibration bench until the new pH cables are shipped 11/30/26. The pH sensor will be calibrated when the new cables arrive early December.
Calibration work has moved to Building 200 Hall D Service Building.
COMMENT ON (SAM26-27) Hall D line BCM Temp controller conversion
connectivity issues were ironed out yesterday and the autotune was completed this morning. cavity is sitting at 110F and holding. All thats left to do is monitor. Consider complete but leaving paperwork open. Should any additional work be needed it will be broadcasted here.
iocsoftljwien restoration failed
iocsoftljwien restoration failed
COMMENT ON Investigate MWF1I04 and MWF1I06 Supplies
CREW CHIEF SIGN IN
THOMAS JEFFERSON NATIONAL ACCELERATOR FACILITY
ACCELERATOR OPERATIONS CREW CHIEF SIGN IN FORM
Date : 11-18-26
Time : 12:09:56
Day : Wednesday
Shift : Day
Crew Chief : Deir
Program Deputy: Merz
Team : A
LERF Operator: 0.000000000000000e+00
Operators :
This stamp certifies that the above Crew Chief has read/reviewed/received the following:
ISB Laser Room Rack Work
Installed the Cards and connected the cables on the rack (see Fig. 1). Riad can check the stability of the attachment and we can modify if needed. The connection should as described in Fig. 2 (see old connection in Fig 2, noting that we have flipped the way it was attached to the Rack).
For Shukui, I have left 10/32 flat head screws of different lengths to attach gormet to the wall (See Fig. 3). Ideally the shorter length should work.
gun vacuum during fan relocation
The fans are definately helping the HV chamber temperature and pressure.
Fig1 shows the gun ion pump current: the step up is when I moved the smallest fan to the suitcase instead of on the HV chamber, the larger increase when I turned off the medium fan to relocate it to the other side of teh chamber, and the decrease when I got that fan turned back on.
Max current 30 nA, likely just hydrogen release from the temporary increase in temperature. Gun monitor thermocouple reached 39C max during the fan motion, now back to 29C.
COMMENT ON BPM Maintenance - SAM '26
prep bake progress
Bake continues well - soaked at 160 set overnight. Highest temperatures about 175. Began a ramp to 185 on the control (a blank 2.75 flange near the HV chamber valve).
Gun vacuum (VIP2I00) slightly elevated. Tee vacuum higher at 79 uA. Suitcase ion pump remains at 0.0-0.1 nA, suitcase temperature 28C.
Bake ion pump recovered from over 200 uA to 38 uA overnight with soak, turbo cart at mid 10-8 Torr range.
If everything continues without surprises, I anticipate soak from ~2 PM today until ~2AM Friday, ramp down and NEG activation on Friday, cool by Monday.
iocsoftmdaq1 restored
iocsoftmdaq1 restored
iocsoftnl09rf restored
Program Deputy Summary, presented 2026-11-18
iocsoftrfhtrdev1 restored
COMMENT ON SAM2026 - Standing Magnet Degradation Study (LDRD+)
The Magnet LDRD group will try to perform a final dosimetry swap-out and set of tunnel measurements after the Thanksgiving break. The first week of December, we will spend several partial days performing magnet measurements and collecting dosimetry.
We will aim to avoid the busiest areas as much as possible.










