Aggregator
COMMENT ON 26/27 SAM Power Supply Flushing
MSSG:
Rebuild of LR1 is completed, testing of unit is underway now, also in process of ZVV at North access and North Linac PS locations (DCP-Delk supporting us). We will be ready to start flushing @North access PS tomorrow and confirmed that does not interfere with DCP scheduled work.
Thanks to all team members.
COMMENT ON East Arc Magnet Flow Measurements
iocsoftwatlowtcdev1 restored
iocsoftwatlowtcdev1 restored
COMMENT ON Plasma processing during the Fall 2026 SAM
iocsoftnl09rf restored
iocsoftnl09rf restored
Program Deputy Summary, presented 2026-11-03
Hall D - Daily report
COMPLETED Install ZA Beam Pipe Restraint
Hall B daily update for 2 NOV 26
MOLLER install 11/2/2026
1L07 Cool Down Complete
COMMENT ON Install 8 kW circulators in 1L09
ATLis Comments Daily Digest
Cryo Daily Update
• 1L07 u-tube installation to support 4K cooldown
• CHL2 lower section of 4K cold box vacuum pump maintenance
• CHL2’s 2K Cold Box process piping – pump & backfills
• CHL2’s 2K Cold Box test fit of new o-ring
• The failed ODH cell in CHL2 Compressor Room was replaced. The new one was calibrated and successfully tested.
COMMENT ON Dominion Energy 40 and 33 MVA Substation PM
ACG Report
NL08 C75 Upgrade: (ACE TEAM) Installed and terminated network cables for the RF server, ups, Cryo diode, rf heater and src vacuum chassis's. Network ports configured. We will install the network cables to the rffcc, hpa, interlock and resonance chassis tomorrow.
Documentation for the new vacuum widget library.










