Aggregator
COMMENT ON Perform HCO of Injector 10 Amp Trim Racks
APPROVED Remove 1L06,07 TL Side PR L-Tubes
Survey and Alignment work summary
COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
COMMENT ON E3 Convectron Controls Upgrade (2026 SAM)
With the success of the fix of the Valve interlock cable between E3 and E5 I have contacted Radcon to install new Radcon screw in rack E301B10 for the new panel holding the new convectron controllers.
Will continue to monitor and perform another HCO at the end of the week along with the Valve interlock controls at E5: https://tasklists.jlab.org/atlis/tasks/121068
If everything checks our I will close out Atlis/PTW.
COMMENT ON E3 to E5 Valve Interlock Cable repair/replacement (2026 SAM)
So far no issues have arisen.
Replaced Valve interlock chassis with original chassis in rack E501B10.
Re-installed original power supply with new fuse for Valve interlock chassis.
Contacted Radcon to get Radcon screw re-installed for this chassis.
Will continue to monitor chassis the rest of the week then close out Atlis/PTW.
HVPS readback strangeness: resolved
The issue reported earlier has been resolved. It was due to an unexpected interaction between the gun HVPS readback PV and the FSD comparator.
The FSD comparator channel which measures the gun voltage (IN01_4 channel 1) had its TEST flag enabled, causing its readback to be stuck at 209 kV. As one readback was stuck and the other was just too high by a relative amount, it was not obvious that there was a common reason for the two readbacks being false.
Gun HV vacuum conditioning: 3rd trip at 185 kV
COMMENT ON MO Outage in Preparation for Bldg 67 Breaker PMs (Affects Bldg 85)
iocsoftrfhtrdev1 restored
HOLD B.67 5-Year Extensive Electrical PMs
In summary from F&O: The primary concern is maintaining adequate condenser water (cooling tower) flow to the ESR Complex. Usually this is accomplished during North Access electrical power outages by operating three condenser water pumps connected to the electrical panel that remains online and restricting water flow to the West ARC and North LINAC LCW heat exchangers.
COMPLETED Install and test sync script for CHL screens on guard9
Gun HV vacuum conditioning: 2nd trip at 183 kV
We continue to see typical gas desorption during gun HV conditioning. The vacuum activities are correlating with decarad counts and anode and gun HVPS current. As soon as the vacuum improves, the decarad counts abates, and gun HVPS current returns back to background level, indicating HV ceramic insulator and cable are happy.
We just experienced our 2nd trip.
Ramping back again!
COMMENT ON Tunnel Arc Magnet Flushing
MSSG:
The team did a real nice job, flushing the second array of dipoles (29/30) and rinsed the array. They completed the job with a nice clean up and put up/staged flush rig and LCW containment. Also, re-labeling of Supply/Return LCW circuits.
Tomorrow work will shift to West Arc septum (ZAs) flushing and containment in blue 55/gal barrels. The new SR1 is now completed and ready for use tomorrow.
Gun HV vacuum conditioning: 1st trip at 172 kV
we are seeing typical gas desorption during gun HV conditioning. The vacuum activities are correlating with decarad counts and anode and gun HVPS current. As soon as the vacuum improves, teh decarad counts abates, and gun HVPS current returns back to background level, indicating HV ceramic insulator and cable are happy.
Ramping back again!










