CEBAF Operations Summaries
Recent Log Entries
- APPROVED Remove 1L06,07 TL Side PR L-Tubes
- Survey and Alignment work summary
- COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
- COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
- COMMENT ON Vacuum Activities CEBAF 9/09/2026 through 12/31/26 (SAM26)
- COMMENT ON E3 Convectron Controls Upgrade (2026 SAM)
- COMMENT ON E3 to E5 Valve Interlock Cable repair/replacement (2026 SAM)
- HVPS readback strangeness: resolved
- Gun HV vacuum conditioning: 3rd trip at 185 kV
- COMMENT ON MO Outage in Preparation for Bldg 67 Breaker PMs (Affects Bldg 85)
- iocsoftrfhtrdev1 restored
- HOLD B.67 5-Year Extensive Electrical PMs
- COMPLETED Install and test sync script for CHL screens on guard9
- Gun HV vacuum conditioning: 2nd trip at 183 kV
- COMMENT ON Tunnel Arc Magnet Flushing










