Recent Log Entries

COMMENT ON Injector Upgrade - Phase 1 Installation (Gun to Chopper)

Log Number: 3856044Logbook(s): Body: 

Day #29, Week 6 Day 4, Wrap-Up:

AIPINJ --
* Gun2 table moved to give room for S&A to lay out new
points
* Gun3 stub + Y-chamber + NEG pedestal removed
* First Wien comm-chassis installed. 3856003
* Yesterday's CED merger prompting further BPM upgrade
work on software side -- BPM system upgrade overall
coming together nicely. 3855971

Other Injector SAD Work --
* PSS upgrades continue
* Viewer upgrades (camera, CAMAC -> VME) continue
* 429MHz amp and PS troubleshooting continues.
3855978

iocse13 restoration failed

Log Number: 3856043Logbook(s): Tags: Body: restorelib 2.2.1 Target restore date was 2020-10-29 17:10:10 The output from the myRestore execution was as follows: iocse13 system@2020-10-29 17:10 2(2) restored seebpm@2020-10-29 17:10 1321(1321) restored SEE_BURT The following are not available in EPICS IOCSE13:do_fill_wire;S IPM2A01.BURT IPM2A03.BURT IPM2A04.BURT IPM2E01.BURT IPM2E02.BURT IPM2E03.BURT IPM4A01.BURT IPM4A02.BURT IPM4A03.BURT IPM4E01.BURT IPM4E02.BURT IPM4E03.BURT IPM6A01.BURT IPM6A02.BURT IPM6A03.BURT IPM6E01.BURT IPM6E02.BURT IPM6E03.BURT IPM8A01.BURT

iocse2 restored

Log Number: 3856041Logbook(s): Tags: Body: restorelib 2.2.1 Target restore date was 2020-10-29 16:27:19 The output from the myRestore execution was as follows: iocse2 system@2020-10-29 16:27 2(2) restored seebpm@2020-10-29 16:27 2773(2773) restored SEE_BURT 64(64) restored Execute: /usr/csite/certified/bin/ced2Epics -ced ced -A -s -i iocse2 (success) Procedure return status: Success

COMMENT ON PSS North Linac Segment PLC Upgrade

Log Number: 3856033Logbook(s): Body: 

Finish assembly of North lanic PLC banks system A and B. Units are now installed into rack MC02B04. Have stared the process, of connecting signals cables to cross connect blocks. Work progressing.

COMMENT ON CPS/HPA circuit identification

Log Number: 3856027Logbook(s): Body: 

Additional steps performed by SSG for each CPS:
Verify that CPS does not receive permissive from PSS.
Take off the PSS Lock.
Allow to perform VVU checks.
Install PSS Lock.

COMMENT ON Magnets Disconnection in North Linac for Girders Removal

Log Number: 3856023Logbook(s): Body: 

We disconnected the magnet leads at 1L21, 1L22,1L23,
1L24 and 1L25 girders.

I was giving permission by Radcon to enter 1L23, 1L24 and
1L25

Tape the leads together, roll up the cables and tied them up
to the cable tray. We place a Magnet Verified De-Energized
label on the girders.

IHAM905 not showing resonable peaks

Log Number: 3856020Logbook(s): Entry Makers: kiarraBody: 

After running the harp through, we noticed the peaks don't look as they should.
Just out of curiosity, we ran IHAM803 -- peaks look great there. Why isn't 905 working?
Is it an amplifier issue?

Also, I just wanted to note that the component list does not include IHAM905 -- so I selected 803.

Follow-up Re: MBHK101H and MHBM502H mismatch

Log Number: 3856018Logbook(s): Body: 

Tightened leads to MBHK101H/V and MHBM502H/V. 101H/V were loose by touch. Took over a turn n a half to tighten the leads at the magnet. Half turns on a 1 or 2 leads on 502H/V at the magnet. Spares are in the control room if needed.

KB

APPROVED Install C-100 style vacuum controls and cabling in zone NL05

Log Number: 3856016Logbook(s): Body: 

From Leo:
The existing vacuum controls for zone 1L05 are on the 4-Zone crate in NL03. We are taking the 1L05 vacuum controls away from the NL03 crate and moving them to a new C-100 style stand alone crate. This means we have to make the old crate "forget" it ever had control of 1L05. These old 4-zone crates all have hand wired back planes that were never intended to be modified. We are essentially performing "brain surgery" on the crate.

Follow-up Re: MHBM702V Mismatch

Log Number: 3856015Logbook(s): Body: 

Inspected the magnet this morning. Tightened the leads to the vertical and horizontal magnet. Maybe a half turn on one or two connections at the magnet. Spares are needed if the card needs to be replaced.

KB

Follow-up Re: RF Interlock Faults not responding?

Log Number: 3856013Logbook(s): Body: 

There were some manual steps necessary to restore FSD functionality. After the quarter has reached GDR gradient, the clear faults button on the cavity exop page must be pushed to clear the ramp fault, then the Master Reset. This will clear the interlocks chassis FSD fault. The node ITMaster FSD node was masked to circumvent this problem earlier. After following the sequence, the node was unmasked and the GDR trip to SEL FSD became functional. I will look to see how to make this process simpler for operations.

APPROVED RSEP9 BREAKER TEST

Log Number: 3856008Logbook(s): Body: 

Once breaker is removed, a temporary cover plate will need to be put in place.

Task approved. Schedule date coincides with other planned outages/work at the SAB. This is a suggestion.

Pages