Gun 2 vacuum work

Recent Log Entries -

Log Number: 3855763Logbook(s): Entry Makers: marcyadderleybullardBody: 

Turned off all ion pumps
Moved prep ion pump to VIP2I01c channel for logging
Vented gun 3 stub, no change in downstream pressure.

COMMENT ON Injector Upgrade - Phase 1 Installation (Gun to Chopper)

Recent Log Entries -

Log Number: 3855747Logbook(s): Body: 

Day #27, Week 6 Day 2, Plans:

Tunnel --
Please keep early Injector area of tunnel -- Gun, laser hut,
up to choppers -- clear for vacuum work.
* Gun Vacuum Work (Marcy+Phil) --
** Venting Gun2 and Gun3
** Replacing 10" flange
** Pumping Gun2 back down
* 3p Videographer Walk-Through

InjSB --
* PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
* Viewer work, IN03B07, 6a - 9a (Norris)
* BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
* CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)

iocitf2 restored

Recent Log Entries -

Log Number: 3855744Logbook(s): Tags: Body: restorelib 2.2.1 Target restore date was 2020-10-27 08:07:35 The output from the myRestore execution was as follows: iocitf2 caen6533@2020-10-27 08:07 108(108) restored blm2@2020-10-27 08:07 48(48) restored systemEnum@2020-10-27 08:07 2(2) restored RasterUITF@2020-10-27 08:07 3(3) restored Execute: /usr/csite/certified/bin/ced2Epics -ced ued -A -s -i iocitf2 (success) Procedure return status: Success

W2 SSA2 update

Recent Log Entries -

Log Number: 3855741Logbook(s): Entry Makers: lfarrishwissmannBody: 

Good Day
We are still troubleshooting the Interface Control Unit for SSA2 it seems to be a low output drive level from the internal preamp module. We will have to LOTO to further investigate this problem.

COMPLETED Disconnect downstairs Hall A SEE bpm harware for Water damage repair work

Recent Log Entries -

Log Number: 3855736Logbook(s): Body: 

Went down to Hall A's alcove this morning and walked the area
where the Water Damage repair work is going to happen. After
talking with Neil Wilson and Steve Suhring yesterday along with
the safety prework walk this morning, I find I do not need to
disconnect any bpm electronics in Hall A for the Water Damage
Repair work. All my bpm hardware and beam line bpm cans are
well out of the work area. Closing this atlis.

UITF A5 And A6 apperture current signals connected

Recent Log Entries -

Log Number: 3855733Logbook(s): Body: 

Finally A5 and A6 appertures have been installed in UITF. I have been waiting some time so that I could connect the current readback wires to these devices. The Picoameters where installed over 8 months ago with Controlled Screens and software support provided by Sue Witherspoon. Current Readback wires connected first thing this morning to A5 and A6 appertures. Beam On!!

COMMENT ON Injector Upgrade - Phase 1 Installation (Gun to Chopper)

Recent Log Entries -

Log Number: 3855725Logbook(s): Body: 

Day #26, Week 6 Day 1, Wrap-Up:

AIPINJ --
* Preparations made to vent gun (full details in 3855719) --
** Cross removed from roughing line that had NEG
** Ionized N2 purge in back of valve where pump cart will
connect tomorrow
** Y-Chamber ion pump moved to gamma supply for
better resolution during vent and valve leak checks
tomorrow
* New wien fixtures w/alignment features for CEBAF and
UITF assembled (pics, full details: 3855679)

Other Injector SAD Work --
* PSS Upgrades (a massive effort) continues