COMMENT ON Install C-100 style Vacuum Controls and Cable Install NL08 (2026 SAM)

7 hours 59 minutes ago
Log Number: 4547919Logbook(s): Body: 

The upgraded gauging that will be installed between 1L08 and 1L09 will have it's controls and cables installed at zone 1L09.
Cabling for these new gauges will be pulled through previously installed smurf tube at 1L09 in penetration #618 under NL09B13 rack.
These smurf tubes already have the HV and controls cables for the vacuum controls system for 1L09.

We are planning on pulling this cable tomorrow morning if staffing/schedule permits.

mathewam

ACG Report

2 days 5 hours ago
Log Number: 4547900Logbook(s): Tags: Body: 

Started RF 3.0 EPICS Controls for the 1L08 C75 Upgrade
Started FSD work for 1L08 C75 Upgrade
New system opspsselog2 installed and verification complete
Deployed a replacement for the Ops group's sick time request form

higgins

iocsoftw3spce restored

3 days 2 hours ago
Log Number: 4547880Logbook(s): Tags: Body: restorelib 3.0.1 Target restore date was 2026-09-18 15:30:53 The output from the myRestore execution was as follows: iocsoftw3spce systemEnum@2026-09-18 15:30 2(2) restored Execute: /usr/csite/certified/bin/ced2Epics -ced ced -A -i iocsoftw3spce (success) PVs modified: 0 PVs modified: 0 PVs modified: 0 PVs modified: 0 PVs modified: 0 PVs modified: 0 PVs modified: 0 Procedure return status: Success
alarms

Shift Information

Shift Day
CEBAF Program
MCC Crew Chief Howard
MCC Operators
Program Deputy Ghosh
Announcements

Access Status

Recent PSS History

recent pss history graph