Aggregator
COMMENT ON Wien filters high voltage evaluation
ACG Report
RF 1L08 Upgrade network infrastructure installation complete
-UPS NMC nl08b12ups01 has been configured.
Verified communication to all RF 3.0 Chassis's in NL08 from the new softIOC "iocsoftnl08rf"
Started design of the new vac-summary screen generator.
COMMENT ON Disconnect, Remove 20 Amp Trim Power Supplies For Bench Repair
Repairs finished, power supplies reinstalled:
E101B08 ch. 7 (MQL1S08)
E301B09 ch. 5 (MQK7A15)
Removed, repaired, reinstalled 4 additional power supplies:
SA01B12 ch 1 (MQL1A38)
SA01B12 ch. 2 (MQK7A31)
SL01B04 ch. 4 (MQK5R07)
SL27B10 ch. 4 (MQL2L27)
Janak, Chaudhary, Humphry
COMMENT ON Tunnel GW Catch Pans
COMMENT ON PSS General maintenance tasks for SAM 2026
C100-02R Acceptance Testing Day Shift
COMMENT ON Upgrade 1L08 to a C75 zone.
We have two items still pending. 1. The optional handle that was purchased for the main breaker in the supply is not compatible, Ernest is in the process of correcting the issue with the supplier. 2. We still need to do a final inspection on our work to insure everything is installed properly and all connections are tight. We will perform that tomorrow.l
MOLLER install 11/4/2026
• Installed cable trays in DAQ bunker.
• Target group install U tubes between mirror and entrance cryo cans.
• Welding in progress for the Main Detector cable tray support
• Welding done for the pivot platform spectrometer girder. Alignment checked by S&A
• Met with Carroll Jones to go over restoring LCW to the nine Hall A magnets.
• As part of waste removal day. Remove flammables from the hall cabinet and helped with CRTs.
Hall C daily summary
Today Hall C technicians worked on.
Painting PCS skids.
Machining MOLER Barite shield wall assembly parts.
Fabricating concrete anchor pieces.
Welding on ENGY mobile detector stand.
Printing and test-fitting and modifying NUCAT parts
Assembling filament extrusion project.
LOTO recertification practical planned for 11/05/2026 after noon.
Cryogenics Work Update
• 1L07 JT valve LVDT Troubleshooting: No issues were identified during troubleshooting.
• Modification of a control valve at HDR
• CHL2 vertical section of 4K Cold Box diffusion pump electrical PM – completed
• HDR cold box vacuum insulation instrumentation troubleshooting
• Prepared for crane for CHL2’s 2K Cold Box crane installation
• Installed a CHL2 cold box relief valve
• LOTO CHL2 C6 for oil pump and motor work










