Aggregator

MOLLER install 11/2/2026

2 days 20 hours ago
Log Number: 4551633Logbook(s): Tags: Entry Makers: jonesBody: 

Installed new bolts on the upstream beamline girder support and leveled the support.
Prepped detector cable stands for aluminum support welding.
Installed boron and plates for the dump viewer shielding.

jones

1L07 Cool Down Complete

3 days ago
Log Number: 4551632Logbook(s): Body: 

Cool down of 1L07 is complete. All temperature diodes are cold and module is beginning to form liquid. LL set to 50% with JT range spanning from 0-90%. SH valve also stepping up to 100% at a rate of 1% every 2 min.

mcgough

Cryo Daily Update

3 days 1 hour ago
Log Number: 4551629Logbook(s): Body: 

• 1L07 u-tube installation to support 4K cooldown
• CHL2 lower section of 4K cold box vacuum pump maintenance
• CHL2’s 2K Cold Box process piping – pump & backfills
• CHL2’s 2K Cold Box test fit of new o-ring
• The failed ODH cell in CHL2 Compressor Room was replaced. The new one was calibrated and successfully tested.

jwilson

ACG Report

3 days 1 hour ago
Log Number: 4551627Logbook(s): Tags: Body: 

NL08 C75 Upgrade: (ACE TEAM) Installed and terminated network cables for the RF server, ups, Cryo diode, rf heater and src vacuum chassis's. Network ports configured. We will install the network cables to the rffcc, hpa, interlock and resonance chassis tomorrow.
Documentation for the new vacuum widget library.

higgins

Hall C daily summary

3 days 2 hours ago
Log Number: 4551623Logbook(s): Body: 

Today Hall C technicians worked on.

Semiannual safety warden inspection in Hall C
Wire rope inspection in Hall C
Weld inspections for PCS magnet skids.
Painting of PCS magnet skids.
NUCAT detector frame fabrication
Printing and test-fitting and modifying NUCAT parts
Assembling filament extrusion project.
Checked out laptop from help desk fro EPAS training
No cross division work planned for 11/03/26

jnines

COMMENT ON Dominion Energy 40 and 33 MVA Substation PM

3 days 2 hours ago
Log Number: 4551619Logbook(s): Body: 

Previous guidance was not turn off anything that can be but rather avoid any high power device operations. High power devices such as cold compressors, Box Power Supplies, and RF High Power Amplifiers. Colleagues should not power off their desk electronics etc. for this work, correct? If so, please amend the description of task to be more precise. Thanks.

moser

COMMENT ON Magnet Disconnect for Electrical Testing of Arc Dipoles

3 days 4 hours ago
Log Number: 4551603Logbook(s): Body: 

All dipoles listed below have been disconnected, and magnet leads have been moved out of the way. The attached checklist has been printed and filled out. The magnet group can now perform their magnet testing.

MJC5A03
MJC5A04
MJC5A21
MJC5A22
MJC5A23
MJC5A28
MJC5A30
MJC5A31
MJA9A03
MJA9A04
MJA9A21
MJA9A22
MJA9A23
MJA9A28
MJA9A30
MJA9A31

-O'Brien, Crespo

kevino

COMMENT ON Install C-100 style Vacuum Controls and Cable Install NL08 (2026 SAM)

3 days 4 hours ago
Log Number: 4551602Logbook(s): Body: 

Re-configured new interlock chain for NL07, NL08 and NL09.
Was able pull back and reuse interlock cable from 6 GeV SRF Vacuum crate to NL09 for NL08.

New configuration for interlock is:
- NL06 (6 GeV) to NL07 (existing cable just re-pinned)
- NL07 to NL08 (cut cable from 6 GeV to NL09 in half)
- NL08 to NL09 (same cable that was cut in half)

Will verify correct interlock chain during HCO/Commissioning.
C100 chassis at NL08 has been powered on in preparations to Network cables being installed this week.

mathewam

Shift Information

Shift Day
CEBAF Program
MCC Crew Chief Richardson
MCC Operators
Program Deputy Merz
Announcements

Access Status

Recent PSS History

recent pss history graph