Aggregator
1L13 largely recovered
Operator SIGN IN
COMMENT ON Rip Rap placement at select outfall
COMMENT ON RF HCO & Gradient Ramp 2026
Vacuum Group Summary 2026-02-19
2L03
- VIP2L03A reconnected to building power
- Valve air lines reconnected
2L25
- New V-blocks installed
- Cleanroom setup slated for tomorrow
MYBBS06
- First leak check passed
- Will pump with cart over weekend, get pressures lower for Monday final leak check and ion pump turn on
COMPLETED HCO 0R08 BCM electronics
COMPLETED Site Honeywell (LCW) Controls Calibrations
COMMENT ON C100-03R (2L25) SRF Cryomodule Commissioning
Completed the LLRF Pre-Commissioning for Cavities:
We verified all interlock checks (ARC, window, vac, HE interlock faults)
and all passed without issue (Leo helped with the vacuum interlock tests)
We also put a small amount of forward power into each cavity in SEL
mode.
We found each cavity to be off machine reference as follows:
cavity 1: 230kHz,
cavity 2: 255kHz,
cavity 3: 186kHz,
cavity 4: 309kHz,
cavity 5: 187kHz,
cavity 6: 267kHz,
cavity 7: 231kHz,
cavity 8:272kHz,
We did not attempt to tune the cavities.
Thank you for all helped : ketchum, bachiman, geesaman, plawski,settl
COMPLETED FY25 Mechanical UCA Repairs
COMMENT ON FY25 Mechanical UCA Repairs
COMPLETED Rip Rap placement at select outfall
COMMENT ON Hall B Dome Shielding
Following a conditions re-evaluation, a construction change request (CCR) has been routed and approved which provides a simple, safe, achievable solution to begin work. Will need to maintain good communication and coordination regarding any vibration-related issues.
The following cavity histories have been updated: 1L18-6
The following cavity histories have been updated:
1L18-6
Username: kerns
Date/Time: 02-19-26_15:31:14
RF Status: Good
Tuner Status: Good
Comment: RFCM replaced for comm. errors. Downloads performed.
Special Instructions:
Maintenance Tag: Component: RFCM {Removed SN: 514, Replacement SN: 351}
CREW CHIEF SIGN IN
THOMAS JEFFERSON NATIONAL ACCELERATOR FACILITY
ACCELERATOR OPERATIONS CREW CHIEF SIGN IN FORM
Date : 02-19-26
Time : 15:18:51
Day : Thursday
Shift : Swing
Crew Chief : Forman
Program Deputy: Buttles
Team : F
Arm : RADCON
Designated SSO: Schaumloffel
LERF Operator:
Operators : Schaumloffel
This stamp certifies that the above Crew Chief has read/reviewed/received the following:
RF Module Downloads
COMMENT ON CHL Control Room Fiber
COMMENT ON Rip Rap placement at select outfall
Autolog restore
The following cavities have been GSET 0: 1L13-2
The following cavities have been GSET 0:
1L13-2
Username: michaelm
Date/Time: 02-19-26_15:08:40
RF Status: Bad
Tuner Status: Good
Comment: GSET 0 - stepped off +100k - Regulation issues. Bad RFCM?
Special Instructions:
Maintenance Tag: Component: RFCM










