iocsoftrffeonset restored
FML SAM 9/10/2025 Updates
Projects
• CUP Upgrade - Continued chiller/pump piping fabrication and install, continued controls migration, continued interior SWGR terminations.
• N/S Access Cooling Upgrade – continuing construction in NAB
Maintenance
• Electrical PM in Hall A: Switchboard SB-ESA PM completed ahead of schedule, panel board PM continues
• Site Honeywell Controls Calibrations – starting in NAB @ 9:30 AM
• Begin NL & WA LCW Pump PMs ~7:30 AM
• SA Cooling Tower cleaning and PM continue
COMMENT ON Upgrade 2L03 to a C75 zone.
Sealed two of three open penetrations with foam before we came up short of foam. ESH has foam on order and will let us know when it has arrived. ODH signage will remain for ODH1 in zone 2L03 until the last penetration is filled downstairs. Techs: C. Kerns, L. Farrish and Adam Schoener. Personal locks removed from MDP breaker and in-line dump.
COMMENT ON Install 8 kW circulators in 2L05 and test into shorts
Disconnected waveguides on the remaining backside 4 cavities (3/4 and 5/6) and installed blanker plates as well as PSS lock bolts. Will need to check waveguide air pressure tomorrow to insure all eight cavity waveguides are holding pressure above .6 PSI Techs: C. Kerns, L. Farrish and Adam Schoener. Personal locks removed from MDP breaker and in-line dump.
COMMENT ON 20 Amp Trim System Preventative Maintenance 2025
iocsoftrffeonset restored
COMMENT ON Power Down and Start PM for 10 Amp Trim System SAM 2025
Started PM on North Access Trim Racks and 20 Amp Power Supplies, Chris Humphrey has started on NA01B06 trim rack and Matt Janak has started on NA01B10 trim rack. I have started on the 20 Amp power supply MQN2A38, we will continue with PM in the morning.
Diggs, Humphrey, Janak
COMMENT ON Power Down and Start PM for 10 Amp Trim System SAM 2025
Seed lasers off
COMMENT ON Building 53-Laser Room Access Control Addition
Vacuum Group Summary 2025-09-09
iocsoftIDXE401 restoration failed
COMMENT ON Site Cooling Tower PMs
Survey and Alignment work summary
COMMENT ON Gun HVPS SF6 tank 75 PSIG relief valve swap with tested / certified valve
Tasks 5-8 performed today in addition to first step in task 9: Evacuated air from HVPS tank to 30 in-Hg and left under vacuum overnight.
Details: https://logbooks.jlab.org/entry/4456732
Plan for tomorrow (09-10-2025): Complete task 9, perform tasks 10 and 11.
COMMENT ON Vacuum Work associated with IHA0L03, IHA0L10 and IHA1A21
Injector: Removed 24 Vdc connectors at VBV0L00B. VBV2D00A, VBV3D00A, VBV5D00A, VBV0L02A, VBV0L03B, VBV0L04A, Opened VBV0L03A with Local Valve Control; VIP0L02A, VIP0L02B, VIP0L03 and VDP/VIP0L03 are turned Off, IHA0L03 change out complete, Pumpdown is started and a Leak Check and VDP Activation will be done tomorrow morning + VIP start-up.