Aggregator
APPROVED Relocate BLM 2L08-11 from Camac BLM card to 2L07 VME based BLM card
APPROVED RF 3.0 HPA Firmware Update
APPROVED Quad Removal BSY Line 1C and 3C
APPROVED Accelerator Warm Region Beamline/Component removal and reinstallation work
APPROVED Site Honeywell (LCW) Controls Calibrations
APPROVED Install 8 kW circulators in 2L05 and test into shorts
APPROVED Inspect All ZA Main Supply & Return Hoses
APPROVED Vacuum Work associated with IHA0L03, IHA0L10 and IHA1A21
APPROVED Harp Assembly Replacement - SAM 2025
COMMENT ON Inspect All ZA Main Supply & Return Hoses
COMMENT ON SAM 25 Magnet Flushing
COMMENT ON Inspect All ZA Main Supply & Return Hoses
Mag Shop:
Just a reminder we will be conducting pre-flush ZA flow checks starting @MZA7R04 in South Linac today. Joe and I will be locking out PS at 730am, having a Pre-Job brief then hitting it. We will reach out to Bern when work is completed there, so he can start flushing. Then we will move down the South and BSY as time permits. Work docs and ZVV will all be completed. Please add to work map.
COMMENT ON Harp Assembly Replacement - SAM 2025
COMMENT ON PSS software updates of TIA portal and iFix
PSS software was updated for NL, SL, and INJ Systems A and B. The BSY update caused communication issues between BSY and the Halls, so the BSY PLC has been placed in stop mode to release the maglocks on access doors and gates. Remaining systems, including BSY, will updated tomorrow.
COMMENT ON Switchover of Existing Central Chilled Water System Chillers and Cooling Tower 58-CT-1 to New JCI Controllers and Programming
Cooling tower controller signal and power wiring completed. Communication wiring still needs to be completed. Verification of cooling tower control points and program testing is still in progress. Chiller system controller work is to begin Tuesday morning at 7:30 AM.
Follow-up Re: Follow-up Re: Laser room entry card reader installation update
SW group installed network cable to CST network switch upstairs, connected to patch panel downstairs and verified connection back to switch. https://logbooks.jlab.org/entry/4456592
Now waiting for authorization to shutdown the panel and continue the work downstairs.
COMMENT ON Gun HVPS SF6 tank 75 PSIG relief valve swap with tested / certified valve
Today we performed tasks #3 and #4. See details in: https://logbooks.jlab.org/entry/4456602
COMMENT ON Install 8 kW circulators in 2L05 and test into shorts
COMMENT ON Upgrade 2L03 to a C75 zone.
Completed cable removal and storage in the cable tray out of the way of cryo-module being removed. Only cable left on the cryo-module were the cavity Cryo diode temp cables that I have a question for SRF about their being disconnected at this time. Arc detectors removed and taken to Ram cart for Rad Survey. Now that Adam Schoene and Alex Shenenberger put foam in upstairs empty penetrations but downstairs will need to be sealed also before signs can be changed back to ODH 0. Techs: Chris Kerns, Larry Farrish and Adam Schoene. Personal locks removed from MDP and inline dump