Aggregator
COMMENT ON Power Down and Start PM for 10 Amp Trim System SAM 2025
APPROVED Install network cable in Injector SB for Laser Hut CANS
APPROVED 2025 Annual overhead crane and rigging inspections
APPROVED Site Cooling Tower PMs
APPROVED N/S Access Power Supply Rooms Cooling Upgrades
COMMENT ON Power Down and Start PM for 10 Amp Trim System SAM 2025
APPROVED 20 Amp Trim System Preventative Maintenance 2025
COMMENT ON SAM 2025 Box Supply Work
APPROVED Replace Chopper Control Chassis
COMMENT ON Diagnose ion pump blips in chopper region
APPROVED Diagnose ion pump blips in chopper region
APPROVED Remove 1L06 utubes
APPROVED Remove 1L05 utubes
APPROVED Remove 1L04 utubes
Program Deputy Summary, presented 2025-09-08
COMMENT ON Building 53-Laser Room Access Control Addition
COMMENT ON Wien filters high voltage evaluation
Log Number: 4456481Logbook(s): Body:
Work re-scheduled to begin 8/22/25 to allow for Injector Vacuum Polarized Section IPPS Upgrade to be completed: https://tasklists.jlab.org/atlis/tasks/117872