Aggregator
COMPLETED 1L09 Heater control investigation
CIS Work Summary 01/07/2026
FML SAM Update 1/08
Survey and Alignment work summary
MOLLER Install Update 01/07/2026
Continued installation of MOLLER LCW system. Hall D continued assembly of the pion donut assembly. Hall A techs moved transport structure for seven-sided ring to laydown yard and dis-assembled.
ATLis Comments Daily Digest
Vacuum Group Summary 2026-01-07
HOLD B63 Repair/replace lighting.
COMMENT ON Miscellaneous RF SAM work
iocsoftihvbs1 restored
COMMENT ON Upgrade 2L03 to a C75 zone.
COMMENT ON Injector CAMAC Card cleanup
COMMENT ON Injector CAMAC Card cleanup
Unseated several cards, and had SSG remove their unused CAMAC node card. I will attach a spreadsheet of cards removed in the next comment. Will leave paperwork open until next monday such that should any hardware need to be reseated, we can do so expeditiously
COMMENT ON Install 8 kW circulators in 2L05 and test into shorts
COMMENT ON B63 Repair/replace lighting.
Electricians will link a new PTW to replace the defective breaker for the E4 lighting circuit in Panel 63-E4-L. Please note that shutting down Panel 63-E4-L will also de-energize Panel 63-E4-PP1. Refer to the attached panel schedules for details. Once we receive clearance to shut down the panels, we are prepared to proceed immediately.