Aggregator
Box Supplies Were Cycled
CIS on call: weekly summary
Calls: none
CIS activities:
- Beam QE scan and spot move with on-call staff training: summary by Marcy #4537606. Submitted the draft procedure to Kathy for finalization.
- tunnel access with Facilities to plan for a new penetration in the laser room wall
Charge lifetime: can't interpret the most recent data yet as the spot move happened only yesterday. But, assuming we get a lifetime similar to before, the new spot position should last us through the run.
HYST AREA 7-0 Cycles Magnets
HYST AREA Version 7-0 has successfully cycled the following:
Area.Linacs.North
Area.Linacs.South
Area.Arcs.Arc1.Spreader
Area.Arcs.Arc1.Arc
Area.Arcs.Arc1.Recombiner
Area.Arcs.Arc1.Extraction
Area.Arcs.Arc2.Spreader
Area.Arcs.Arc2.Arc
Area.Arcs.Arc2.Recombiner
Area.Arcs.Arc2.Extraction
Area.Arcs.Arc3.Spreader
Area.Arcs.Arc3.Arc
Area.Arcs.Arc3.Recombiner
Area.Arcs.Arc3.Extraction
Area.Arcs.Arc4.Spreader
Area.Arcs.Arc4.Arc
Area.Arcs.Arc4.Recombiner
Area.Arcs.Arc4.Extraction
Box Supplies Were Cycled
The following box supplies were CYCLED by version 2-16 of the Box Supply Cycling Script:
ARC1A Ramp Rate = 8.127 A/s
ARC2A Ramp Rate = 6.808 A/s
ARC3A Ramp Rate = 9.725 A/s
ARC4A Ramp Rate = 10.989 A/s
ARC5A Ramp Rate = 9.961 A/s
ARC6A Ramp Rate = 9.222 A/s
ARC7A Ramp Rate = 10.222 A/s
ARC8A Ramp Rate = 11.962 A/s
ARC9A Ramp Rate = 9.370 A/s
ARCAA Ramp Rate = 12.581 A/s
RSEP8A Ramp Rate = 10.612 A/s
RSEP9A Ramp Rate = 3.273 A/s
XSEP2T Ramp Rate = 5.803 A/s
XSEP4T Ramp Rate = 5.311 A/s
XSEP6T Ramp Rate = 9.492 A/s
XSEP8T Ramp Rate = 17.786 A/s
XSEPAT Ramp Rate = 16.605 A/s
Autolog restore
Autolog save
Autolog save
Saved: janak 08-05-26 11:42:12 {A:i B:1 C:5 E:1060 A=BS B=BS C=Tune D=BS 0R08=5.07 A B C dump(s) in. 3R10 spikes mitigated. Orbit needs cleanup} { } ALL
Comments: Reduced 3R10 spikes, but still need considerable time to clean up orbit.
COMMENT ON Rotate WA LCW Pumps
Task did not happen during Tuesday's MD - Manpower diverted to emergency response elsewhere.
This is a high priority task - WA LCW pump currently in operation has developed bearing / coupling noise and vibration and should be taken out of service as soon as reasonably possible.
COMPLETED Ground Water Removal From Trench Under Racks in NL SB (Bldg. 1)
"4 hour escalation notifications made"
This is in regards to the linked tuning downtime.
We are still running into 3R10 blm trips. We've tried numerous steering solutions and we'll think we've solved it for a bit and then the blm trips will pop back up. Optics on-call is here helping usdiagnose the problem. We will try to steer for 15 more minutes and if we can't find an answer we'll download an allsave from before the 3R10 blm issues started popping up and see if that puts us in a better place.
Fopt 26aug051031 results
Comment:
HOSTNAME: opsl01
CED WORKSPACE: OPS CED LOGIN KEY: pro
MYA DEPLOYMENT: ops
CONFIG PATH: /cs/prohome/apps/q/QTSnyder_QT5/1-2/fileio/config/cs.conf
DIFORB PATH: /usr/ntfs/public/optics/diforb
MQA9S01 off design
Fopt
Hall C RadCon Checklists
Even Orbit Lock BPM issue Diagnosis Update
I am investigating the even orbit locks causing steering issues. IPM2A05, 6A04, 8A04, and AA04 BPM (iocw3se1) is locking onto a signal when beam is not present and is producing extreme oscillating position (5mm) swings when running Tune Mode @ ~4.8uA. I believe the noise that is being locked onto is swamping the true Tune Mode beam signal. When they are running Tune Mode Beam and when Beam is OFF the YGAIN values are within 20 counts of each other this is not normal of course. This is where I believe the problem resides.
COMMENT ON RF Maintenance for the week of August 3rd through August 9th, 2026
Replaced arc det. PMT in 1L14-7 that was failing manual arc tests. After verifying voltages at interface chassis, tested good 3 times. Also replaced arc detector on 1L04-2 that had been knocked off during maintenance. Examined tube and didn't see damage so I rehung it and it also tested good x3.
Machine Update
Update: We are still having issues with BLM 3R10
HYST AREA 7-0 Cycles Magnets
HYST AREA Version 7-0 has successfully cycled the following:
Area.Linacs.North
Area.Linacs.South
Area.Arcs.Arc1.Spreader
Area.Arcs.Arc1.Arc
Area.Arcs.Arc1.Recombiner
Area.Arcs.Arc1.Extraction
Area.Arcs.Arc2.Spreader
Area.Arcs.Arc2.Arc
Area.Arcs.Arc2.Recombiner
Area.Arcs.Arc2.Extraction
Area.Arcs.Arc3.Spreader
Area.Arcs.Arc3.Arc
Area.Arcs.Arc3.Recombiner
Area.Arcs.Arc3.Extraction
Area.Arcs.Arc4.Spreader
Area.Arcs.Arc4.Arc
Area.Arcs.Arc4.Recombiner
Area.Arcs.Arc4.Extraction