COMMENT ON Install MOLLER JLab Production RTP HV Driver
Can you provide information on what a "day" is (24hrs or an 8hr shift)? It appears this activity will take 7 "days". If we are able to perform other beam related tasks at any time during this 7 day period can you document that in your ATList, or do you need the full 7 days with no other Injector beam activity taking place? Need to know for planning purposes. However, if you do need the full 7 days with no activity can this be performed during the > 2 weeks "Off" during the change from low energy to high energy run?