CIS on-call: no change to laser output or gun high voltage on power blip
ioc outages, potential iocse17 hardware failure
I was called to investigate multiple iocs related to Hall C that went down, as well as Synch30Hz alarms on iocmc1 and iocse17.
iocmc1 seems to be healthy apart from the Synch30Hz alarm. This alarm probably doesn't indicate a problem on the ioc itself but instead shows that the 30Hz loop is not making it back to iocmc1 due to an interruption somewhere else, possibly iocse17 or iocse20.
Downtime Incident CLOSED: Hall B Vacuum at 2H04
Hall C Power meters: 96-SWBD-ESC2 dropped to 0 at 6:55
Box Supplies Were Cycled
The following box supplies were CYCLED by version 2-16 of the Box Supply Cycling Script:
ARC1A Ramp Rate = 8.126 A/s
ARC2A Ramp Rate = 6.939 A/s
ARC3A Ramp Rate = 9.912 A/s
ARC4A Ramp Rate = 10.993 A/s
ARC5A Ramp Rate = 10.439 A/s
ARC6A Ramp Rate = 9.385 A/s
ARC7A Ramp Rate = 10.490 A/s
ARC8A Ramp Rate = 11.966 A/s
ARC9A Ramp Rate = 9.717 A/s
ARCAA Ramp Rate = 12.243 A/s
RSEP8A Ramp Rate = 10.612 A/s
RSEP9A Ramp Rate = 9.498 A/s
XSEP2T Ramp Rate = 5.809 A/s
XSEP4T Ramp Rate = 5.314 A/s
XSEP6T Ramp Rate = 9.568 A/s
XSEP8T Ramp Rate = 18.009 A/s
XSEPAT Ramp Rate = 16.595 A/s
iocse17 restored
Owl Shift Beam Charts
Owl Shift FCAL problem channels
Main RF and Box supplies back up
The OPS DRVHs for the following cavities have been updated: 1L22-2
The OPS DRVHs for the following cavities have been updated:
1L22-2
Username: samari
Date/Time: 04-21-25_07:54:00
RF Status: Good
Tuner Status: Good
Comment: DRVH=18.000 Jumped the gun, waited until KRRP dropped and was able to restore to 18 MV/m
Previous OPS DRVH: 16.5
Special Instructions:
iocse17 restored
MQK7R07 Regulation Error
CREW CHIEF SIGN IN
THOMAS JEFFERSON NATIONAL ACCELERATOR FACILITY
ACCELERATOR OPERATIONS CREW CHIEF SIGN IN FORM
Date : 04-21-25
Time : 07:50:11
Day : Monday
Shift : Day
Crew Chief : Mock
Program Deputy: Nguyen
Team : B
A crew chief in training will be stamping in.
Arm : Barker
Designated SSO: Shenenberger
LERF Operator:
Operators : Barker, Shenenberger, Shriner
The OPS DRVHs for the following cavities have been updated: 1L22-2
1L22-2 KRRP High
Walking back the cavity after everything tripped. Had to hand optimize klystron phase due to the KRRP trips it would cause at any GLOS. was able to get it into SELAP at 10 MV/m but I'm going to stop walking it up at 16.5 (DRVH=18) due to KRRP getting near 150 Watts.
VCG1L23 Tripped Again
VCG1L23 Faulted again last week and went to reset the controller. Same issue found as last time. Gauge might need to be replaced: https://logbooks.jlab.org/entry/4349845
Systems that went down
CREW CHIEF IN TRAINING SIGN IN
THOMAS JEFFERSON NATIONAL ACCELERATOR FACILITY
ACCELERATOR OPERATIONS CREW CHIEF IN TRAINING SIGN IN FORM
Date : 04-21-25
Time : 07:33:11
Day : Monday
Shift : Day
Crew Chief In Training : Schoene
Crew Chief On Duty : Mock
Program Deputy: Nguyen
Team : X
Arm : Shenenberger
SSO: Barker
LERF Operator:
Operators : Barker, Mock, Shenenberger, Shriner