Feed aggregator
COMMENT ON Check and Adjust Current and Voltage readbacks, locally and remotely on all Legacy CPS.
After further troubleshooting the calibration of the analog read backs for the voltage and current of zone 1L15 was completed. Also the calibration of both the digital and analog voltage and current read backs for zone 1L16 were completed. Further troubleshooting required for calibration of the current overload circuit.
iocse4 restored
COMMENT ON Injector Upgrade - Phase 1 Installation (Gun to Chopper)
COMMENT ON South Access Meter and PMs
COMMENT ON North Access Meter and PMs
We have been postponing this work to avoid the possibility of disrupting the ESR; now that they will be shutting down the ESR for several days I would like to take advantage and schedule the North Access outages to coincide with the ESR outage. I have entered this for February 3 and 4.
IPM6A13.XSOF
UITF LLRF testing
Investigation of low frequency AM instabilities in cav1 and cav2 field:
Found measurable cross-talk between RF testing cables (Super Flexible SLC) . Because we are measuring AM modulations in the range of 0.05% , cross-talk level was enough to corrupt the results.
Cables have been replaced and cavity filed stability measurements show very good results:
AM modulation < 0.03 % RMS
Integrated phase noise < 270 fsec ( integrated between 1Hz-3 MHz)
most prominent mechanical modes at 3.6 Hz, 11 Hz, 22 Hz
COMMENT ON Injector Upgrade - Phase 1 Installation (Gun to Chopper)
Days #76, Week 15 Days 5, Summary:
Tunnel/ISB
*IB-T panel job for chopper amps completed successfully
*Phil/Bubba prepped tunnel for fire pipe install next week, ready to go
*Scott powered Wien racks back up
*Shukui planned to power up laser room hardware again today
TL/TED
*Carlos tested V-Wien opposite polarity +/- 19 kV good, VWien ready for girder when needed
*Viewer cylinder mods delaying A1/A2 girder assembly, ETA ~1 week delay
*Waiting on Thomson rods mods from shop to finish PCUP assembly
*Marcy planned to finalize plan for baking HD and QW coils with Lakshmi
MMF
*H-Wien mapping in
COMMENT ON Trim Utility Chassis Upgrade - All CEBAF Trim Racks
Simon Wood, Jason Delk and I tested (2) more upgraded
Utility Chassis in the UITF trim rack IT07.
The first chassis would turn on and ramp to 25V then trip
off; it happen twice, so Simon and I try the second chassis
and it worked OK. We ran the chassis through all stages of
the test procedure and it pass all stages.
So Jason and I reinstalled the first chassis again, and this
time both bulk power supplies ramp up to 30V.
We ran the chassis through all stages of the test procedure
and it pass all of the stages.
The (2) chassis where place in the machine at E101B11
and E201B11
S.
COMMENT ON *Vacuum Activities CEBAF 03/03/20 through
2L09, 2L10 Heater Calibration are beginning
Global 4ch BPM SuperCal Performed
Global 4ch BPM SuperCal Performed
Global 4ch BPM SuperCal Performed
Global 4ch BPM SuperCal Performed
iocea3 restored
Global 4ch BPM SuperCal Performed
Global 4ch BPM SuperCal Performed
COMMENT ON Shutdown of Panel I-BT in the Injector
Pages
