After chopper recovery and setup beams A, B and C are setup to the inline dump.
Set up the choppers as well as I could. We need more time to check steering and dechopping. However, we should be good for the program at hand which is beam to A, B and D. If RF group changes the chopper 1Y system (amplifier change or something else) tomorrow, then we need to check things again. Therefore I see no point in spending too much time now.
Figures 1,2,3 are A beam zero posed
Figure 4,5 are B beam
Figure 6,7 are D beam
A save with orbit lock and energy locks on for A Beam is done. 25767