Program Information
Recent Log Entries
- Follow-up Re: Progress on fixing instrument air leaks on injector viewer instrument air
- COMMENT ON Vacuum Activities CEBAF 2/18/2025 through 2/18/26
- applied LOTO to gun HVPS breaker
- COMMENT ON Routine Maintenance of ODH Systems (Managed by SSG).
- COMMENT ON B53 Shut down Panel IB-PP3. Replace broken breaker and terminate new breaker for Injector Helium Vent Damper in same panel.
- ODH head OMA03 at Hall A - Dome has been placed back in service.
- Survey and Alignment work summary
- SOFFs for IPM0I07 Modified
- SOFFs for IPM0I06A Modified
- SOFFs for IPM0I06A Modified
- COMMENT ON 67-ACC-1 HVAC Repair (cools Rm 100)
- COMMENT ON North linac Insulating vacuum leak checks
- APPROVED Repair leak and clean FA system terminals at station 420
- COMMENT ON Accelerator service building mechanical PM's
- COMMENT ON (B67) Shutdown Panel 67-NA-1-A: Roll Phase A&C CTs on power meter