COMMENT ON Inj. 1/4 CM - Booster Swap

Log Number: 4153410Logbook(s): Body: 

Last 2 remaining girders removed, the 2 girder stands and their base plates have been removed, the girder pedestal was also removed yesterday, and all adjuster cartridges have been removed from the girder stands and pedestal. Area has been swept and there are no obstructions on the floor.

COMMENT ON Modify 0L02 RF drive system for booster upgrade

Log Number: 4153403Logbook(s): Body: 

Larry Farrish "This morning replaced all waveguide air supply hoses in the new zones NL21-26, except the main supply at the top of the ceiling I will get a taller ladder for that next week.
Waveguide in the Injector has been taken down, I will continue to disconnect cabling from module next week."

PSS Firmware Updates continuing

Log Number: 4153368Logbook(s): Body: 

PSS firmware updates continuing in the MCC and progressing well.
Completed checks of Injector and NL segments.
Also updated the Firewall to permit OPC/UA traffic for future use.
On Friday will complete Hall A, Hall B and Hall C segments.

status phase2 injector work Day 4

Log Number: 4153337Logbook(s): Body: 

finished disconnecting all water lines from phase2 beamline, plugged the supply and return lines at the manifold, water back on, no leaks
Disconnected the water to buncher (ball valves inside the tunnel, along cable tray above chopper). Now there’s a leak at one of the supply lines at chopper2 cavity. Small leak, I turned OFF water flow.
All magnets and I&C stuff now disconnected
Larry removed most of the waveguide, thanks
Prepped the removal of the spectrometer beamline for tomorrow

Work preformed in the SAD

Log Number: 4153306Logbook(s): Entry Makers: lfarrishBody: 

This morning replaced all waveguide air supply hoses in the new zones NL21-26, except the main supply at the top of the ceiling I will get a taller ladder for that next week.
Waveguide in the Injector has been taken down, I will continue to disconnect cabling from module next week.

COMMENT ON Install and HV process 200 kV electron gun

Log Number: 4153301Logbook(s): Body: 

Particle counter shows 50-100 inside the clean hood.
Krypton evacuated between the bottle regulator and leak valve at the gun. I left the Kr line under vacuum for now.
After evacuating Kr line, connected pump cart to right angle valve upstream of gun overboard IP. Right angle valve remains closed of course. Started pumping on the line at ~ 11 am.
All of these tasks are in preparation for venting and removing HV chamber on Monday 03/27/23.

COMMENT ON BO dipole magnet mapping - SAD 2023

Log Number: 4153283Logbook(s): Body: 

Magnet Measurement:

We teamed up on the MBO dipole and have removed it from Injector beamline and carefully removed the hall chips.

Matt has some fit checks to do at UITF. If you need 1006 magnet steel for new return legs, just let us know.

If not, we will see it when you drop off @MMF for QA and Magnetic Measurements.

Matt P./ Scott B./ Mike B.

COMMENT ON Plasma processing in CEBAF accelerator

Log Number: 4153271Logbook(s): Body: 

Once the OSP is signed by the stakeholders, it would be helpful to attach one to this ATLis as the link will get buried in the comments section as updates come in. Also, a printed copy at the processing site wouldn't hurt either.